Construction

Duration of construction

Construction of the Sopi-Tootsi wind farm began in early 2023 with land improvement work. In the first phase, all the necessary preparations were made for building the foundations and installing cables. The foundations were completed in February 2024, and the wind turbines were set up over six months, from April to September. The wind farm is expected to reach full production capacity in the first quarter of 2025.

Impact of construction on daily life

There are no residential buildings close to the wind farm, so the construction work will not cause significant disruption to local residents.

The most noticeable impact will be increased traffic on roads near the settlement of Tootsi and on Tööstuse Street in Tootsi. Drivers are advised to stay alert and follow temporary traffic signs during the construction period.

Construction timeline

2023
February
Start of the construction of roads and crane sites
2023
June
Start of the construction of foundations, start of the construction of solar park
2023
July
Start of electrical work
2023
December
Installation of frames for the solar panels
2024
January
Installation of the solar panels
2024
March
Installation of the solar park's inverters
2024
May
Transportation and installation of wind turbines
2024
September
All wind turbines are set up, and the wind farm starts production
2025
First half of the year
Testing and precision setup of the wind turbines
2025
Second half of the year
The solar park starts production